Grain Bin and Elevator Construction
Anton Bayer Millwright uses the Bainter hydraulic jacking system to erect their 
grain bin construction projects.  We start by constructing the bin roof with a 
rolling scaffold/jacking system, once that is completed we then install the 
hydraulic jacks and begin raising the grain bin, 32" at a time, installing rings and 
stiffeners with each lift and re-set.  Once the bin is completely erected, we then 
anchor it down using a epoxy anchoring system.  This anchoring system far 
exceeds the structural requirements for wind load and grain pressure.  The bin 
unloading auger, aeration fan, and perforated floor is then installed.  Once this is 
complete, the grain bin can be immediately filled with whatever grain product it is 
purposed for.  
Hopper bottom tanks have a slightly different construction procedure but the 
basic principle remains the same with the exception of a crane being used to set 
the tank on the hopper bottom and super structure.
        
        